Flashcube building
The "Flashcube" building at 720 Main was completed in 1972 and has been vacant a dozen years.

Flashcube Building Apartment Project Expects to Start Early 2019

August 17, 2018  |  Kevin Collison  |  3 min read

By Kevin Collison

The planned redevelopment of the historic “Flashcube” building into apartments has hit a “profound” budget jump due to price increases for construction materials and labor, raising the cost by 38 percent to $69 million.

In response, a request by the developer, Worcester Investments, to have its “prevailing wage” labor goal set at 20 percent was approved by the Planned Industrial Expansion Authority Thursday, but not without some pushback.

“My issue is the labor cuts, they seem to be the first thing,” said board member Kevin O’Neil. “You’re already getting a full, 100 percent abatement.

Last year, the PIEA board approved a 25-year property tax abatement for the project, which calls for the redevelopment of the nine-story, building at 720 Main St. into 184 apartments and 35,800 square-feet of commercial space.

Since then, budget costs have jumped substantially and the project is no longer pursuing financing from the U.S. Department of Housing and Urban Development. HUD sets the prevailing wage component at 100 percent.

The prevailing wage is in a community is established by the U.S. Department of Labor.

“We want to move forward with the historic nature of the Flashcube building, but our biggest concern is managing costs,” said Matt McCauley, Worcester chief operating officer.

Charles Renner, the attorney representing Worcester, said the developer is now pursuing private financing for the project.

And in response to O’Neil’s concern about labor, Worcester officials said reducing labor costs had not been their first choice to save money.

Jim Calvert, director of development and construction, said the project has been redesigned to save money. He added that costs also have risen due to environmental remediation work and building deterioration.

And in a reference to current global economic political climate, Calvert said concern of a tariff war have caused the price of steel to rise.

To sweeten the appeal of the redevelopment project, the developer has agreed to increase the number of what were described as affordable units from 25 to 40. Those apartments will rent for an average of $1,187 per month.

McCauley said Worcester plans to begin work on the project at the beginning of 2019 with completion expected in mid- to late 2020. McCownGordon Construction is the contractor.

It’s nicknamed the Flashcube because of its reflective glass exterior. The former office building has been vacant a dozen years. It was built as the Executive Plaza Office Building in 1972 and is on the National Register of Historic Places.

Don’t miss any downtown news, sign up for our weekly CityScene KC email review here.

Tags:

Reading these stories is free, but telling them is not. Start your monthly gift now to support Flatland’s community-focused reporting.

Kansas City Cooks as Site for National Anti-ICE Dinner Series

October 15, 2026

Celebrated chefs from throughout the metro collaborated for three nights on dinners that raised money for a local immigrant-rights nonprofit.

Related Stories

Kansas City Police Chief Stacey Graves talks Tuesday, Sept. 1, 2026 about her pending retirement. (Carlos Moreno | KCUR 89.3)

Nick’s Picks | Top Cop, Mission Mall, Lucas’ Travels and More …

Nick Haines also has the lowdown on information for the upcoming election, the arrival of fall and Kansas City's Day of the Dead celebration.

Read More >
Starting in January, I-70 will shut down in both directions, along a 4-mile stretch between downtown and the Truman Sports Complex. The Missouri Department of Transportation holds a public meeting on the closure Tuesday. (Screenshot)

Nick’s Picks | I-70, Tax Break, School Petition, and More …

An Interstate 70 closure, a tax rebate for Jackson County property owners, a school closure petition, and more ...

Read More >

Kansas City Helping Renters Avoid Eviction

On any given Thursday, a small hallway in the Jackson County Courthouse crowds with tenants, landlords, and attorneys arriving for their scheduled hearings and trials. The scene unfolds on Floor 7M, which is half the height of the building’s other levels, and is where Associate Circuit Judge Mary Weir recently worked through 55 eviction cases…

Read More >