Final Barney Allis Plaza Rebuild Plan Has $112.4M Price Tag

January 20, 2022  |  Kevin Collison  |  5 min read

By Kevin Collison

Almost three years after launching its search, the city now has solid design plan and price tag for reviving the crumbling Barney Allis Plaza, but appears to be no closer to figuring out how to pay for it.

At a briefing to a Council committee Wednesday, consultants said the Plaza built in 1955 in the heart of the downtown convention district could be rebuilt to “world-class” condition with a smaller, 600-space underground garage for $112.4 million.

Peter Sloan, the HOK senior principal working on the project, total the Council Finance and Infrastructure Committee the Plaza design was the culmination of years of community meetings.

“The goal is making sure we create a world-class destination for all members of the downtown area,” he said.

“We want to elevate the current experience for all residents, employees and visitors. It’s creating essentially a Swiss Army knife of utilization for the city at a park level and an event level.”

A schedule indicated if the Council approves the design and a financing plan by late spring, construction could begin this Fall with a Winter 2024 opening. City officials originally had hoped to have a revamped Barney Allis ready for the 2023 NFL Draft.

The $112.4 million Barney Allis rebuild plan would strengthen the foundation for a potential residential project shown in upper left. (Rendering from HOK)

“We’re at a point right now where we delivered the schematic design, guaranteed maximum price and development schedule,” said William Crandall of CBC Real Estate.

“We know what it’s going to cost but we don’t yet have it figured out how we’re going to finance that.”

The design prepared by HOK calls for the Plaza to be lowered to street level and include a 37,000 square-foot event lawn and plaza that could accommodate up to 5,000 people along with water features, play space, a dog park and public art.

The current 980-space, three-level garage which has been partially closed for several years because of deterioration would be replaced with a 600-space garage. The plan also would strengthen the foundation to allow construction of potential residential tower.

Braces were installed to shore-up the deteriorating lower levels of the Barney Allis Plaza underground garage. (Photo from TranSystems report)

The cost of doing nothing also was made clear.

In April 2020, an engineering consultant had recommended the city immediately close the garage, citing structural problems and code violations.

The city then spent $3 million to shore up and patch the facility although the lowest level of the garage remains closed.

City Architect James Freed told the Council members the temporary fixes don’t alter the garage’s long-term problems.

“The garage remains on life support,” he said. “It’s stable, but there are certainly concerns the amount of deterioration on underside of second floor is substantial.”

He pointed to the collapse last summer of condominium building in Surfside, Fla. that killed 98 people as an example of potential structural risk.

A large pavilion is proposed the northwest corner of the Plaza. It could be replaced with a residential project if one were to move forward. (Rendering from HOK)

“It was a catastrophic failure,” Freed said, referring to the Florida accident. “We have no reason to believe the lower level of Barney Allis Plaza garage would have a significant failure.

“What I need to share is we’ve learned the floor systems are tied into the perimeter walls so if at any time the third floor would have a failure it could risk the perimeter walls that retain the dirt around the streets.”

The consultants also suggested several potential trims to the Barney Allis Plaza and garage proposal that would save about $20 million, the largest being eliminating 200 spaces from the garage, reducing the price by $12.7 million.

Another option that was discussed and discarded was eliminating the underground garage altogether. Freed estimated it would cost $30 million to remove the garage and fill its cavity.

City officials however, have warned that Barney Allis Plaza and its garage were used as collateral in the debt financing of Bartle Hall, and removing the parking would violate its terms. Nearby hotels also have contractual parking agreements.

Barney Allis Plaza was described in a 2018 report by the Urban Land Institute as an unwelcoming place.

How to pay for the rebuild remains a quandary.

When the Council approved funding last March to further study what was then estimated as a $70 million project, there had been anticipation it would be eligible for funding from the federal infrastructure program.

While Washington has approved a massive infrastructure bill since then, there has been no indication the Barney Allis plan was included or could qualify.

“I know this is a priority of the Downtown Neighborhood Association and the Downtown Council, not so much the parking, but the public space on top,” said Councilman Eric Bunch.

“This is a tough one based on the (city) financial circumstances.”

The consultants recognized the Council members would experience sticker shock regarding the final cost estimate.

“We realize that’s a big lift and a big ask, but it’s an important part of the city’s hotel and convention network,” Crandall said.

An overview of the features planned for Barney Allis Plaza (Rendering from HOK)

Tags:

Reading these stories is free, but telling them is not. Start your monthly gift now to support Flatland’s community-focused reporting.

Nick’s Picks | Fan Fest, Streetcar, Liquor and More …

June 8, 2026

World Cup Begins The wait is finally over. The first ball of the 2026 World Cup will be kicked Thursday, ushering in 5 ½ weeks of competition across the United States, Canada and Mexico. It’s also opening day for Kansas City’s FIFA Fan Fest at the National World War I Museum and Memorial—our first real…

Related Stories

Nick’s Picks | Messi, Jail, Buses, and More …

World Cup Team(s) Arrive It’s starting to feel real. The first World Cup team has landed in Kansas City. Defending champions Argentina touched down at KCI airport on Sunday and will begin practicing today at Sporting KC’s training facility in Wyandotte County. Much of the attention, of course, is focused on Lionel Messi. The soccer…

Read More >
The Heart of the Nation exhibit in the IKEA store in Merriam, Kansas, "celebrates the extraordinary work of artists, art educators and cultural leaders ... that define Kansas City's evolving artistic landscape." Jeremy Bell's work is part of the exhibit.(Mike Sherry | Flatland)

World Cup ‘Statement Piece’ Evokes Best Version of Kansas City

Before I moved to Kansas City almost 56 years ago, I had been here only once — for a brief visit to the Kansas City Press Club when I was attending the University of Missouri School of Journalism. But because of that visit and the fact that I grew up in the Midwest (Woodstock, Illinois,…

Read More >
The Center for Digital Inclusion's Technology Education Program helped Jodi Whitt break a cycle of incarceration. (Taylor Doyle | Flatland)

KU Center Helps Women Gain Foothold After Incarceration

A flier from her probation officer was the turning point for Jodi Whitt, who had spent more than two decades in and out of the criminal justice system. The piece of paper introduced Whitt to the Technology Education Program offered by the University of Kansas’ Center for Digital Inclusion. Since 2019, Whitt has risen through…

Read More >